The weighted average cost of capital (WACC) is the weighted
average cost of a firm’s capital structure (Mian & Vélez-Pareja, 2008).
This is a company’s cost of equity and the cost of debt added together.
According to Mian and Vélez-Pareja (2008), there are complications with the
calculations for WACC however these are mainly due to misinterpretation and
misuse by companies. Reducing WACC is something companies aim to accomplish and
EDF Energy are no different.
EDF Energy are currently undergoing construction of a new
nuclear power station called Hinkley Point C which is projected to cost roughly
£22 billion (The Financial Times, 2019b). This is a significant amount of money
and so financing will be an issue for EDF Energy. On top of that, Hinkley Point
C, as well as other projects in France and Finland, have been plagued with
problems, causing long delays and extra unexpected costs (The Financial Times,
2019b). The problems with these projects have seen their share price in France
drop by almost 39% in the last year (The Financial Times, 2019b) (Yahoo Finance,
2019).
Electricite de France S.A. (EDF.PA) share price over the last 12 months. Source: Yahoo Finance
Due to these high project costs, raising capital to fund
these projects can be very difficult, especially because they won’t be making
any money until the construction is complete. For this reason, EDF are very interested
in different methods of raising finance (The Financial Times, 2019a).
One of the methods of financing these new nuclear power
stations, one of which is Sizewell C, EDF’s new proposed project which will be
identical in design to the currently under construction Hinkley Point C, is
using the Regulated Asset Base system (The Financial Times, 2019a) (The
Financial Times, 2019c). The Regulated Asset
Base model allows a company to take money from customers bills who are going to
be using the service in order to finance a large-scale project. In return, customers
will receive a cheaper, more reliable service once the project is complete. The
company can also receive subsidies from the government as part of this model as
well as raise cash from pension funds that accept a much lower return on
investment (Makovšek & Veryard, 2016) (The Financial Times, 2019c). This is
a system which is mainly used by utilities such as gas, water and airports (The
Financial Times, 2019c). There is also usually a regulatory body which sets
price caps in order to ensure companies don’t abuse the Regulatory Asset Base
System in order to make a higher profit (Newbery, 1997).
However, according to The Financial Times (2019a), using the
Regulated Asset Base model for funding new nuclear energy projects is ‘far from
convincing.’ This is because the regulated asset base model is mainly used in
industries with a proven track record of being reliable. For example, water
projects also require large-scale investment and are an important part of our
country’s infrastructure. Yet, there is little construction risk for water
projects whereas the construction risks for nuclear projects are high and, as
shown by EDF’s current construction projects such as Hinkley Point C, they
often suffer from delays and extra costs due to complications (The Financial Times,
2019a) (The Financial Times, 2019b). Also, the Regulated Asset Base system has never
been used for a project as lengthy as a nuclear power station and so it is
relatively untested in such a long, complicated project (The Financial Times,
2019c). This shifts the risk of the
project from the company to the customers as those are the ones who will end up
paying upfront over the duration of the project and so if there were any
additional costs or delays, it would be the consumers who suffer (The Financial
Times, 2019c) Also, if the project was to be scrapped half-way through
construction, there is no guarantee that the consumers will receive any of
their money back (The Financial Times, 2019c).
EDF are actively encouraging the government to allow them to
use the Regulatory Asset Base System for their planned construction of Sizewell
C (The Financial Times, 2019c). EDF are claiming the use of the Regulatory Asset
Base System could reduce their WACC (The Financial Times, 2019c).
Source: The
Financial Times
EDF have calculated the use of the Regulatory Asset Base
model can reduce their WACC from 9.2% (Hinkley Point C project) to around 6% (for
Sizewell C) (The Financial Times, 2019c). Also, EDF have argued that the reduction
in cost of capital for the project would allow them to sell their electricity
at a much lower price, making nuclear energy more affordable (The Financial Times,
2019c).
In Conclusion, the use of the Regulatory Asset Base system
in the nuclear energy industry would be extremely beneficial for companies like
EDF, allowing them to raise capital easier and reduce their WACC as well as offset
their risk to customers (The Financial Times, 2019c). However, the use of the
Regulatory Asset Base system could spell trouble for customers because,
although they may receive cheaper rates for nuclear energy if planned nuclear
projects are successful, nuclear projects are notoriously plagued with setbacks,
adding additional costs and lengthy delays. This could cause customers to lose
out as they are taking on the risk of the project as opposed to companies like
EDF (The Financial Times, 2019c).
Reference List
Makovšek, D., & Veryard,
D. (2016). The Regulatory Asset Base and Project Finance Models.
Mian, M. A., &
Vélez-Pareja, I. (2008). Applicability of the classic WACC concept in practice. Latin
American Business Review, 8(2), 19-40.
Newbery, D. M. (1997).
Determining the regulatory asset base for utility price regulation. Utilities
Policy, 6(1), 1-8.
The Financial Times. (2019a). How
can we pay for new nuclear power stations? | Financial Times. Retrieved from https://www.ft.com/content/4b81682e-cf19-11e9-99a4-b5ded7a7fe3f
The Financial Times. (2019b). EDF
increases Hinkley Point C nuclear plant costs | Financial Times. Retrieved from
https://www.ft.com/content/92102452-df62-11e9-9743-db5a370481bc
The Financial Times. (2019c). EDF
seeks to charge customers upfront for UK nuclear plants | Financial Times.
Retrieved from https://www.ft.com/content/f9a96304-e980-11e8-885c-e64da4c0f981
Yahoo Finance. (2019).
Retrieved from https://uk.finance.yahoo.com/

A very informative read Lewis! Interesting to read into how EDF are financing their new projects, do you think the implementation of the regulatory asset base system will be successful for EDF? I'll be interested to see if their lower estimated WACC level will be achieved.
ReplyDeleteYes, I do think that the implementation of the regulatory asset base will be successful for EDF. I believe the current government is very keen on implementing this model in order to make nuclear energy more affordable. If implemented, I do think EDF's WACC will reduce however it will be interesting to see how it affects their consumers as nuclear projects have a poor track record when it comes to keeping to budget and staying on time.
Delete